  • The paper introduces common dewatering methods of long—distance gas transmission pipelines at home and abroad.Commissioning technology and requirements of gas pipeline are described from four aspects of implement program/field preparation,dewatering,gas displacement and pressure boosting.Primary factors influencing on drying time are analyzed.Estimation method for drying period,flowrate and gas volume accumulation needed in gas displacement are given.