Nitrogen Separation Technique Applied in Zibo-Laiwu Gas Transmission Pipeline
-
-
Abstract
Through the nitrogen separation case in the commissioning of Zibo-Laiwu Gas Transmission Pipeline (76.8 km in length, 355.6 mm in diameter, 4.0 MPa), this paper discusses the reliability and economy of nitrogen separation program for gas pipeline before commissioning. The article considers the nitrogen separation program as a safe practice compared to non-separator program.
-
-