苏士才. 对美国热媒炉的验收与测试[J]. 油气储运, 1987, 6(1): 38-42.
引用本文: 苏士才. 对美国热媒炉的验收与测试[J]. 油气储运, 1987, 6(1): 38-42.
Su Shicai. Inspection and Test of the Heater with thermal medium U.S.A[J]. Oil & Gas Storage and Transportation, 1987, 6(1): 38-42.
Citation: Su Shicai. Inspection and Test of the Heater with thermal medium U.S.A[J]. Oil & Gas Storage and Transportation, 1987, 6(1): 38-42.

对美国热媒炉的验收与测试

Inspection and Test of the Heater with thermal medium U.S.A

  • 摘要: 文章介绍了美国伊克利伯斯公司400×41.868MJ热媒炉被引进后, 中美双方的交接、验收与测试工作。文中简介了美国这套热煤炉的加热系统与流程图, 对测试、计算方法及测点布置等进行了详细的说明。在测试、计算原油获得的有效热量时, 由于测试时间所限, 我方在计算烟气过剩空气系数、排烟热损失、化学不完全燃烧、机械不完全燃烧损失等方面均采用了简化公式。文章还给出了热媒炉系统各单体设备的散热量, 并根据测试的数据绘制了设备表面温度散热量曲线。文章最后, 着重介绍了1986年1月25日在熊岳泵站测试的全部数据, 并指出在该设备的经济负荷、超负荷能力及超负荷时间、排烟温度偏低、配套仪器、控制系统、附机设备等方面尚存在着一定的问题亟待解决, 以便使这套引进设备更好地为输油生产服务。

     

    Abstract: The article deals with the delivery, inspection and test of 400×41.868MJ Heater Witth thermal medium made in ICOLIBES Company U.S.A with American on one side and Chinese on the other. It briefs the heating system and flow path scheme, and explains in detail the ways to test it and how to calculate, as well as the general layout of test points. While testing and calculating the effective heat, the Chinese side, thinking the test time limited, makes use of simplified formulas to calculate the cotient of the extra air in smoke, the smoke heat loss, the chemical and mechanical inadequate burning loss. It also gives out in the article, the heat rejection of every single unit of the whole system and works out the curve of the surface temperature heat based on measured data. In the end, the article presents all the data measured at Xiong Yao pump station on January 25, 1986, and points out some problems urgently to be solved in economical load, overload capacity, overload time, exhaust gas temperature, instruments associated, control system, and the accessories supplied along with it, in order to have this imported equipment better serve oil transportation.

     

/