肖心遥. 从中——洛输油管道看管中管的保温效果[J]. 油气储运, 1987, 6(1): 23-30.
引用本文: 肖心遥. 从中——洛输油管道看管中管的保温效果[J]. 油气储运, 1987, 6(1): 23-30.
Xiao Xinyao. The Insulation Effect of pipe-In-Pipe as Shown in Zhong-Lo Pipeline[J]. Oil & Gas Storage and Transportation, 1987, 6(1): 23-30.
Citation: Xiao Xinyao. The Insulation Effect of pipe-In-Pipe as Shown in Zhong-Lo Pipeline[J]. Oil & Gas Storage and Transportation, 1987, 6(1): 23-30.

从中——洛输油管道看管中管的保温效果

The Insulation Effect of pipe-In-Pipe as Shown in Zhong-Lo Pipeline

  • 摘要: 中原至洛阳输油管道(以下简称中—洛线), 采用了聚氨酯硬质泡沫塑料(以下简称聚酯泡塑)另加黄夹克作外套——构成管中管的保温结构。在中—洛线试运行和投产使用过程中, 显示了管中管保温效果要优于以往的沥青防腐层的保温效果, 通过对全线总传热系数K和总导热系数K′的计算(包括投产前管中管总导热系数的试算、投产期间总导热系数的测算), 作出了K′值的上下变化趋势的曲线图, 也印证了输油管道通过不同地质区段时有不同的K′值。同时, 由最大的K′值确定中—洛线温度最低、摩阻最大的卡脖子地段。文章最后, 通过最低、最高输油量、加热站的确定、停输时间的分析和计算证明了管中管的保温效益: 使管线的最低输量比原设计降低了30%;使中—洛线有可能甩掉一部分加热站, 因而可节约大量燃料油; 使中—洛线的允许停输时间提高了三倍。除此之外, 文章也指出了管中管保温结构及施工质量的不足之处。

     

    Abstract: The pipeline from Zhong Yuan to Lo Yong (hereafter refered to as Zhong-Lo pipeline) was insulated with polyurethane hard foam plastic (hereafter refered to as foam plastic) coated by yellow jacket constiuting such structure as pipe sheathed by another one. In the commisioning of Zhong-Lo pipeline, it is clearly shown that this way of insulation is superious over the convetionnal asphalt coating in effect. It is through calculation of the general heat transfere coeffcient K and thermo conductivity K′ (including the trial calculation of thermal conductivity before it being put into production and the estimation of it during operation) that the K′ dluctuation curve has been obtained, veryfying the supposition that K′ values vary in different gedlo- gical areas. Meanwhile the bottle-neck' section along Zhong-Lo pipeline is determined by the greatest K′ value, which is lowest in temperature and greatest in friction. Through determination of the minimum and maximun throuthut, numbers of heating stations, analysis of shutdown time and necessary calculation concerned, the advantages revealed are: the minimum throughput has been raised by 30% in comparison with the former design; cutting down a number of heating stations so as to save a great deal of fuel; three times that of the previous shutdown time allowable Besides, the article points out the defects in structure as well as construction of sucha way of insulation.

     

/

返回文章
返回