孙勇, 赵国辉, 游泽彬, 李秋娟, 崔茂林, 刘朝阳. 中俄东线中段天然气管道投产技术探讨[J]. 油气储运, 2022, 41(11): 1312-1318. DOI: 10.6047/j.issn.1000-8241.2022.11.010
引用本文: 孙勇, 赵国辉, 游泽彬, 李秋娟, 崔茂林, 刘朝阳. 中俄东线中段天然气管道投产技术探讨[J]. 油气储运, 2022, 41(11): 1312-1318. DOI: 10.6047/j.issn.1000-8241.2022.11.010
SUN Yong, ZHAO Guohui, YOU Zebin, LI Qiujuan, CUI Maolin, LIU Chaoyang. Discussion on commissioning technology for the middle section of China-Russia Eastern Gas Pipeline[J]. Oil & Gas Storage and Transportation, 2022, 41(11): 1312-1318. DOI: 10.6047/j.issn.1000-8241.2022.11.010
Citation: SUN Yong, ZHAO Guohui, YOU Zebin, LI Qiujuan, CUI Maolin, LIU Chaoyang. Discussion on commissioning technology for the middle section of China-Russia Eastern Gas Pipeline[J]. Oil & Gas Storage and Transportation, 2022, 41(11): 1312-1318. DOI: 10.6047/j.issn.1000-8241.2022.11.010

中俄东线中段天然气管道投产技术探讨

Discussion on commissioning technology for the middle section of China-Russia Eastern Gas Pipeline

  • 摘要: 为提升超大口径长输天然气管道投产效率,加强风险管控措施,优化投产资源配置,针对中俄东线天然气管道长岭—永清段(简称“中俄东线中段”)投产压差高、投产时间长、设备操作频繁等特点,对其投产过程进行优化,提升管道投产的可操作性和各节点风险的可控性。中俄东线中段投产过程中采用站场两级调压方式解决投产调压阀门压差过大的问题;通过规范调压阀门保温装置安装要求,提高蒸汽换热效率,降低调压阀门冰堵风险;针对长输天然气管道提出“先干线后站场”的站场天然气置换方式,减少夜间操作风险,便于开展现场稳压检漏工作;为保证管道氮气封存压力,采用注氮车方式向管道注氮时,应充分考虑液氮资源准备裕量。研究结果可为超大口径长输天然气管道工程投产提供参考与借鉴。

     

    Abstract: In order to improve the commissioning efficiency of long-distance natural gas pipeline with ultra-large diameter, strengthen the risk control measures and optimize the configuration of commissioning resources, the commissioning process of China-Russia Eastern Gas Pipeline (Changling–Yongqing Section) (hereinafter referred to as "the middle section of China-Russia Eastern Gas Pipeline") was optimized based on the large pressure difference of commissioning, long commissioning time and frequent equipment operation, to enhance the commissioning operability of pipeline and the risk controllability of each node. During the commissioning of the middle section of China-Russia Eastern Gas Pipeline, a two-stage pressure regulation method was adopted in the station to solve the problem of excessive pressure difference of the pressure regulating valve. Meanwhile, the efficiency of steam heat exchange was improved by regulating the installation requirements for the insulation device of the pressure regulating valve, and thus the ice blocking risk of the pressure regulating valve was effectively mitigated. Besides, a natural gas replacement mode of "trunk line first and then station"was proposed for the long-distance natural gas pipeline, so as to reduce the risk of operation at night and facilitate the work of pressure stabilization and leak detection on site. In order to maintain the pressure of nitrogen seal, the adequacy of liquid nitrogen resource should be considered, if nitrogen is injected into the pipeline through a nitrogen injection vehicle. Generally, the research results could provide reference to the commissioning of long-distance gas pipeline with ultra-large diameter.

     

/

返回文章