李印, 陈雪见, 姜俊浩. 大型地下水封洞库运营期涌水量计算与注浆设计[J]. 油气储运, 2022, 41(7): 847-851, 858. DOI: 10.6047/j.issn.1000-8241.2022.07.013
引用本文: 李印, 陈雪见, 姜俊浩. 大型地下水封洞库运营期涌水量计算与注浆设计[J]. 油气储运, 2022, 41(7): 847-851, 858. DOI: 10.6047/j.issn.1000-8241.2022.07.013
LI Yin, CHEN Xuejian, JIANG Junhao. Calculation on water inflow of large underground water-sealed storage during operation and grouting design[J]. Oil & Gas Storage and Transportation, 2022, 41(7): 847-851, 858. DOI: 10.6047/j.issn.1000-8241.2022.07.013
Citation: LI Yin, CHEN Xuejian, JIANG Junhao. Calculation on water inflow of large underground water-sealed storage during operation and grouting design[J]. Oil & Gas Storage and Transportation, 2022, 41(7): 847-851, 858. DOI: 10.6047/j.issn.1000-8241.2022.07.013

大型地下水封洞库运营期涌水量计算与注浆设计

Calculation on water inflow of large underground water-sealed storage during operation and grouting design

  • 摘要: 洞室涌水量预测长期以来始终是困扰洞库建设与运营的一大难题,且施工过程中涌水量预测未能与注浆封堵有效结合,容易造成施工期间注浆费用超标、洞库验收困难等问题,严重影响地下洞库的设计、施工及运营。以某地下水封洞库为例,根据地质条件和地下工程布置情况,首先利用FEFLOW软件建立渗流场模型,模拟计算得到未经过注浆封堵条件下的洞库运营期涌水量,并与经验公式计算结果相互验证,确定涌水量推荐值为10 115 m3/d。结合相关规范要求反算渗透系数,整个库区的平均渗透系数需从1.1×10-5 cm/s降至1.09×10-6 cm/s,从而有针对性地指导注浆设计。该研究首次将涌水量计算与渗流控制相关联,可准确估算预注浆工程量,指导施工组织设计,有效解决了同类工程普遍存在的涌水量超标而难以验收投产的难题。

     

    Abstract: Prediction of water inflow in caverns has been a big problem for a long time, and the predication during construction has not been effectively combined with the water sealing by grouting, resulting in excessive grouting cost and difficulty in acceptance of storages during construction, which have caused great problems to the design, construction and operation of underground storages. Herein, a seepage field model was firstly established by FEFLOW software based on the actual geological conditions and the layout of underground works of a underground water-sealed storage, the water inflow of the storage during its operation without water-sealing by grouting was calculated by simulation, and the recommended water inflow value was finally determined to be 10 115 m3/d through the mutual verification with the calculation results of the empirical formula. Further, the permeability coefficient was calculated according to the requirements of relevant specifications. Definitely, the average permeability coefficient of the whole storage area needed to be reduced from 1.1×10-5 cm/s to 1.09×10-6 cm/s, which could guide the grouting design in a targeted way. The calculation of water inflow and seepage control were correlated in the research for the first time, capable of accurately estimating the quantity of pre-grouting and guiding the construction organization design, thus effectively overcoming the common difficulty in acceptance and commissioning of similar projects due to excessive water inflow.

     

/

返回文章
返回